  PROCEDURE FOR LAYING  
 
  1. Determining the position of wall in both vertical and horizontal lines. At the edge of the column, use dowel bar for proper bonding of blocks and column as normal.

  2. Cleaning and soaking with water required for SUPERBLOCK masonary and only 5 mm. thick SUPERBLOCK mortar is enough to bind the blocks together. Mix 2 1/2 parts of glue Mortar to1 part of water by volume.

  3. SUPERBLOCK can easily be cut with a normal Hand Saw (Carbined tips hand saw would last much longer and result best).

  4. After laying blocks with SUPERBLOCK Glue Mortar, making sure all gaps are filled with glue mortar and SUPERBLOCK should be laid overlapping each other and hammer for more stronger.

  5. It's easy to cut and chase in SUPERBLOCK masonary for laying Electrical and Sanitary pipes etc.

  6. For cost saving, plastering thickness should not be over 10 mm. in 2 layers, and must be applied after a gap of one day between the two coats.




   





  PROCEDURE FOR PLASTERING  
 
1. Mix 2 parts of ready mixed plastering mortar to 1 part of water by volume, and stir thoroughly

2. Clean & wet thoroughly the SUPERBLOCK wall before applying the first layer of 5 mm thick ready mixed plastering mortar.

3. Second layer of plastering mortar must be applied at least one day after the first one, giving the desired smooth/rough finish

4. Nailing and anchoring can be done after only 3 days of curing.
 
   





  TOOLS  
 
  1. Cutting Guide

  2. Mortar Mixer

  3. Glue Mortar Spreader (Trowel)

  4. Chasing Tool

  5. Carbined Tips Hand Saw

  6. Bucket